Optimistic duration is the estimation of the maximum amount of time that it would take to perform a task.

A) True
B) False

Correct Answer

verifed

verified

Forward scheduling establishes a project start date and then schedule forward from that date. Based on the planned duration of required tasks, their interdependencies and the allocation of resources to complete those tasks, a projected project completion date is calculated.

A) True
B) False

Correct Answer

verifed

verified

Which of the following is the estimate of the longest amount of time it would take to perform a task?


A) maximum duration
B) optimistic duration
C) pessimistic duration
D) expected duration
E) latest completion

F) C) and E)
G) None of the above

Correct Answer

verifed

verified

An expectations management matrix is a tool for helping management understand the dynamics and impact of changing project parameters such as cost, schedule, scope and quality.

A) True
B) False

Correct Answer

verifed

verified

A PERT chart depicts the WBS or Work Breakdown Structure.

A) True
B) False

Correct Answer

verifed

verified

A Gantt chart is a simple horizontal bar chart that depicts project tasks against a calendar.

A) True
B) False

Correct Answer

verifed

verified

_________________ is a strategy for correcting resource overallocations.

Correct Answer

verifed

verified

Joint project planning (JPP) is a hierarchical decomposition of the project into phases, activities and tasks.

A) True
B) False

Correct Answer

verifed

verified

Milestones have no duration.

A) True
B) False

Correct Answer

verifed

verified

The critical path for a project is that sequence of dependent tasks that have the largest sum of most likely durations. The critical path determines the earliest possible completion date of a project.

A) True
B) False

Correct Answer

verifed

verified

________________ is the unexpected growth of user expectations and business requirements for an information system as the project progresses.

Correct Answer

verifed

verified

Change is frequently a point of contention between the customer and the information systems organization, because they disagree on whether a particular function is a change or a part of the initial agreement.

A) True
B) False

Correct Answer

verifed

verified

________________________ measures the actual amount of time that it takes to complete a task, taking into account that workers cannot possibly perform at 100% efficiency, and that interruptions increases the amount of time it takes from start to finish to complete a task.

Correct Answer

verifed

verified

Elapsed time

Elapsed time takes into account which of the following factors?


A) people cannot work at 100% efficiency
B) people experience interrupts such as phone calls, visitors or other activities
C) people need lunch breaks
D) people possibly participate in other non-project related work
E) all of these

F) B) and D)
G) B) and C)

Correct Answer

verifed

verified

Which of the following is NOT a likely reason for a change in project scope?:


A) availability of better technology
B) users or management want the system to do more than originally requested
C) the expectations management matrix is correct
D) the funding for the project has been reduced
E) none of these

F) All of the above
G) A) and C)

Correct Answer

verifed

verified

Rapid application development (RAD) is a strategy wherein all project stakeholders participate in a short duration project management workshop, which results in a consensus agreement on the project scope, schedule, resources, budget and quality.

A) True
B) False

Correct Answer

verifed

verified

Which of the following is considered a project resource?


A) people
B) services
C) facilities
D) money
E) all of these

F) A) and B)
G) A) and C)

Correct Answer

verifed

verified

Over-optimism is the tendency for systems analysts and project managers to fail to recognize that project slips in one phase or activity can cause corresponding slips in many other phases and activities, and contribute to cost overruns.

A) True
B) False

Correct Answer

verifed

verified

"Identify Business Requirements" is an example of a milestone.

A) True
B) False

Correct Answer

verifed

verified

False

Which of the following is NOT one of the five basic questions that influence project scope?:


A) what product is wanted
B) the efficiency of each of the team members
C) when should the product be delivered
D) what resources are available for the project
E) none of these

F) A) and B)
G) C) and E)

Correct Answer

verifed

verified

B