Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) maximum duration
B) optimistic duration
C) pessimistic duration
D) expected duration
E) latest completion
Correct Answer
verified
True/False
Correct Answer
verified
True/False
Correct Answer
verified
True/False
Correct Answer
verified
Short Answer
Correct Answer
verified
True/False
Correct Answer
verified
True/False
Correct Answer
verified
True/False
Correct Answer
verified
Short Answer
Correct Answer
verified
True/False
Correct Answer
verified
Short Answer
Correct Answer
verified
Multiple Choice
A) people cannot work at 100% efficiency
B) people experience interrupts such as phone calls, visitors or other activities
C) people need lunch breaks
D) people possibly participate in other non-project related work
E) all of these
Correct Answer
verified
Multiple Choice
A) availability of better technology
B) users or management want the system to do more than originally requested
C) the expectations management matrix is correct
D) the funding for the project has been reduced
E) none of these
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) people
B) services
C) facilities
D) money
E) all of these
Correct Answer
verified
True/False
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) what product is wanted
B) the efficiency of each of the team members
C) when should the product be delivered
D) what resources are available for the project
E) none of these
Correct Answer
verified
Showing 1 - 20 of 97
Related Exams